Necessary work on Europaboulevard from May 21 to August 31, 2024
In the coming months, necessary work will take place on the Europaboulevard in Amsterdam from May 21 to August 31, 2024.
Europaboulevard, a major traffic artery in Amsterdam, is undergoing these works as necessary for infrastructure improvements in the city. The RAI, as an important player in the area, is closely involved in consultations about these works.
Due to the nature of the work and other ongoing projects in the area, there is limited room to shift. The City of Amsterdam will therefore establish detour routes using the familiar yellow signs to direct traffic.
When?
In order to minimize inconvenience to customers, organizers and local residents, we have prepared clear maps from the RAI. These maps provide detailed information about the detour routes and will be shared so that people are aware in advance of possible inconvenience and can easily find alternative routes. The maps can be found here and at the end of this article.
- Phase 1: Tuesday 21 May to Friday 7 June
Municipality of Amsterdam will close the S109 from de Boelelaan towards the RAI. - Phase 2: Monday 17 June until Friday 12 July
Municipality of Amsterdam will close the road in the direction ofricht A10. - Phase 3: Monday 15 July until Friday 9 August
Municipality of Amsterdam will close the road from the A10 exit towards the RAI. - Phase 4a: Saturday 10 August to Friday 16 August
Municipality of Amsterdm will close the S109 Buitenveldert towards de Boelelaan between the A10 on- and off-ramps. - Phase 4b: Wedneday 14 August until Saturday 17 August
Municipality of Amsterdam will close the S109 towards Buitenveldert. The entire A10 exit ramp is currently closed. They are working on the road from 21:00 on Wednesday, August 14 until 05:00 on August 17. - Phase 5: Saturday, August 10 until Saturday, August 31
Municipality of Amsterdam will close the S109 from the A10 exit in the direction of Buitenveldert.
Although the municipality strives to make the work as smooth as possible, some disruption is unavoidable. There may be longer arrival and departure times for traffic in the area. However, the municipality remains in close consultation with all parties involved, including RAI, to minimize the inconvenience.
For questions regarding the work, please contact the organizing party, the City of Amsterdam. You can also find additional information on the website of the municipality of Amsterdam.
www.amsterdam.nl
Floor plans overview
Floor plan of phase 1 - May 21 to June 7
Floor plan of phase 2 - June 17 to July 12
Floor plan of phase 3 - July 15 to august 9
Floor plan of phase 4 - Aug 10 to Aug 17
Floor plan of phase 5 - Aug 19 to Aug 31